Question: QUESTION 2 . 2 DESCRIPTION: You are the project manager for a flat complex. The activity table below shows the sequence of activities and the

QUESTION 2.2 DESCRIPTION: You are the project manager for a flat complex. The activity table below shows the sequence of activities and the interdependence. Note (hint): When you calculate the S-curve, use the early start as reference. Use the cost column. Study the Activity Table below and execute the following: Activity Table ID DESCRIPTION PREDECESSOR Resources TIME# COSTS RESPONSIBLE A Receive Scope & Budget NONE 11 R30,000(You) B URS Received & signed off A 11 R30,000(You) C Feasibility Study A 12 R60,000 Outsourced D System Software Spec. B,C 15 R150,000 Annie (reports to PM) E Application S/W Planning B,C 34(complete) Fani (reports to Annie) F S/W License Design & Plan D,E 34(complete) Jan (reports to Fani) G Application S/W Design D,E 35(complete) Andrew (reports to PM) H MRP Gap Analysis (SPRINT) F,G 34(complete) Fani I Customisation of Apps S/W H 46(complete) Jan J Client - Programming Teams H 95(complete) Sifiso (reports to Fani) K Test Server Module Tests I,J 1012(complete) Peter (reports to PM) L Quality Management K 52(complete) Annie M Hand-over & Training L 32(complete) Fani TOTAL # Time in WEEKS (Consider all resources employed at R30,000/week)1. Complete the COSTS column in the table below and add the TOTAL. 2. YOU are the project manager and not all are reporting directly to you, draw a simple Organogram (not organisational breakdown structure)3. Draw a project network that includes all the activities. 4. Show the critical path 5. Calculate the total slack (SHOW the total Slack)6. Draw a master schedule (use costs, early start figures)7. Upload resources and develop a resource histogram. 8. Develop an S-curve based on the information.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!