Question: You are the project manager for a flat complex. The activity table below shows the sequence of activities and the interdependence. Note ( hint )
You are the project manager for a flat complex. The activity table below shows the sequence
of activities and the interdependence.
Note hint:
When you calculate the Scurve, use the early start as reference. Use the cost column.
Study the Activity Table below and execute the following:
Activity Table
ID DESCRIPTION PREDECESSOR Resources TIME# COSTS RESPONSIBLE
A Receive Scope & Budget NONE RYou
B URS Received & signed off A RYou
C Feasibility Study A R Outsourced
D System Software Spec. BC R
Annie reports to
PM
E Application SW Planning BC complete Fani reports to
Annie
F SW License Design & Plan DE complete Jan reports to Fani
G Application SW Design DE complete Andrew reports to
PM
H MRP Gap Analysis SPRINT FG complete Fani
I Customisation of Apps SW H complete Jan
J Client Programming Teams H complete Sifiso reports to
Fani
K Test Server Module Tests I,J complete Peter reports to
PM
L Quality Management K complete Annie
M Handover & Training L complete Fani
TOTAL
# Time in WEEKS
Consider all resources employed at Rweek
Complete the COSTS column in the table below and add the TOTAL.
YOU are the project manager and not all are reporting directly to you, draw a simple Organogram
not organisational breakdown structure
Draw a project network that includes all the activities.
Show the critical path
Calculate the total slack SHOW the total Slack
Draw a master schedule use costs, early start figures
Upload resources and develop a resource histogram.
Develop an Scurve based on the information.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
