Question: Question 2. 2. If the indirect cost for each duration are $1,500 for 17 weeks, $1,450 for 16 weeks, $1,400 for 15 weeks, $1,350 for

Question 2. 2. If the indirect cost for each

Question 2. 2. If the indirect cost for each duration are $1,500 for 17 weeks, $1,450 for 16 weeks, $1,400 for 15 weeks, $1,350 for 14 weeks, $1,300 for 13 weeks, S1,250 for 12 weeks, $1,200 for 11 weeks, and $1,150 for 10 weeks, what is the optimum cost-time schedule for the project? What is the cost? Activity Normal Time Normal Cost A B C D EE E F G H | Crash Cost (slope) 0 100 60 40 0 30 20 60 200 Maximum Crash Time 0 2 1 1 0 2 1 2 1 3 4 3 4 2 3 2 4 2 150 200 250 200 250 200 250 300 200 B B 2 H 4