Question: Question 2 2 Points Which activity should be crashed first to cut one day from the project's duration; calculate the added cost and total cost

Question 2 2 Points Which activity should be

Question 2 2 Points Which activity should be crashed first to cut one day from the project's duration; calculate the added cost and total cost of project. A First activity to be crashed is Flooring, added cost is $ 500, total cost is $ 52650 B First activity to be crashed is Flooring, added cost is $ 500, total cost is $ 53150 First activity to be crashed is Electrical, added cost is $ 1850, total cost is $ 54500 D First activity to be crashed is Paint, added cost is $ 1250, total cost is $ 53900