Question: Two activities on the same critical path are candidates for crashing on a CPM network. Activity details are in the table below. To cut one

so activities on the same critical path are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from e project's duration, activity. should be crashed first, adding to project cost. A. Two, $500 B. One; $6,800 C. Two; $5,000 D. Ono, $800 E. One or Two should be crashed; $1,300 activities on the same critical path are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from project's dutation, activity should be crashed first, adding to project cost. A. Two, $500 B. One: $6,800 C. Two; $5,000 D. One, 5800 E. One or Two should be crashed; $1,300