A new project is being planned to build a bridge across the Clinch River in Kingston. The Project Manager is concerned with how the rising and lowering of the water level by TVA could impact project productivity. As he considers how to plan for this in the project schedule this is considered a what?
Assumption
Constraint
Issue
Risk