Question: QUESTION 2 2 table [ [ Item , table [ [ Usage per ] , [ Parent ] ] , table [

QUESTION 22
\table[[Item,\table[[Usage per],[Parent]],\table[[Lead Time (in],[weeks)]],\table[[Beginning],[Inventory]],Lot Size Rule],[J,,3,0,L4L],[K,2,2,40,L4L],[L,4,1,60,L4L]]
The end product J is made from components K and L. The authorized MPS calls for 10J to be completed in week 4. What is the gross requirement for K?
 QUESTION 22 \table[[Item,\table[[Usage per],[Parent]],\table[[Lead Time (in],[weeks)]],\table[[Beginning],[Inventory]],Lot Size Rule],[J,,3,0,L4L],[K,2,2,40,L4L],[L,4,1,60,L4L]] The end product