Question: Question 2 (20%): A precedence table is given below for a process with 6 tasks, their immediate predecessors and their task times: Immediate Task time

Question 2 (20%): A precedence table is given

Question 2 (20%): A precedence table is given below for a process with 6 tasks, their immediate predecessors and their task times: Immediate Task time label predecessors minutes) 2.0 1.5 2.0 3.0 15 2.0 Daily working time is 14 hours. The daily output need is 210 piece a) Draw the relationship structure of these tasks? 8) Calculate the cycle sims? Use the line balancing technique to determine the number of stations and arrange these tasks to each station? Calculate the efficiency of this system