Question: Question 2 - 20 points The following network diagram represents a project: E A B a. Calculate the ES, EF, LS, and LF times and

Question 2 - 20 points The following network

Question 2 - 20 points The following network diagram represents a project: E A B a. Calculate the ES, EF, LS, and LF times and slack for each activity. Write your computed values in a table similar to the table provided below. b. In addition, identify the critical path and the amount of time needed to complete the project. Activity ES EF LS LF Slack Critical? (Yes/No) A B D E F G Time (Days) 3 2 6 5 4 3 5 0 3 3 5 9 10 13 3 5 9 10 13 13 18

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!