Question: QUESTION 2 ( 3 . 0 0 points ) Develop a resource schedule for the project network below, which requires a team of programmers for

QUESTION 2(3.00 points)
Develop a resource schedule for the project network below, which requires a team of programmers for its development. However, only 5 programmers are available.
Use the parallel method and the followirif heuristics to develop a schedule for the project: 1. Shortest slack. 2. Shortest duration. 3. Smallest identification number.
a) Present the project's workload. Report eventual resource overallocations. (1.50 point)
b) Present a new workload for the project. What is the new critical path and project duration after rescheduling the resources? (1.50 point)
Create the origional load chart and the rescheduled load chart
 QUESTION 2(3.00 points) Develop a resource schedule for the project network

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!