Question: Question 2 ( 3 . 0 0 points ) Develop a resource schedule for the project network below, which requires a team of programmers for
Question points Develop a resource schedule for the project network below, which requires a team of programmers for its developmentHowever, only programmers Activity Subtitle ES EF SLACK RESOURCE SLACK LS DURATION Use the method and the following heuristics to develop a schedule for the project Shortest slack Shortest duration Smallest identification number Create the project's workload Report eventual resource overallocations point Create a new workload for the project What is the new critical path and project after rescheduling the resources point