Question: Question 2 ( 3 0 % ) : You have a 3 0 K M stretch of Highway x ( splits of 1 K M

Question 2(30%):
You have a 30KM stretch of Highway x(splits of 1KM). Assuming identical resources, Draw the LOB for the following project. Perform the LOB calculations and calculate the total project duration. At day 130, haw many KMs would be completed for each activity and how many KMs would be 100% complete? Estimate the status of completion for each activity and for the project at day 180.
\table[[Activity,IPA,\table[[Duration per cycle],[(days/KM)]],\table[[Total duration],[(days)]]],[A,--,3,90],[B,A,4,120],[C,A,2,60],[D,B, C,3,90],[E,D,4,120],[F,D,2,60],[G,E,5,150],[H,F,1,30],[I,G, H,3,90],[J,I,2,60]]
Question 2 ( 3 0 % ) : You have a 3 0 K M stretch

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!