Question: Question 2 3 ( 1 0 points ) In reviewing the project plan, a project professional sees that the first prototype must be completed by

Question 23(10 points)
In reviewing the project plan, a project professional sees that the first prototype must be completed by October 12. This would be best classified as a
project target.
limit item.
milestone.
project objective.
critical goal.