Question: Question 2 3 1 Point The technique that uses optimistic, pessimistic, and realistic time to calculate the expected time for a particular task is called:

Question 23
1
Point
The technique that uses optimistic, pessimistic, and realistic time to calculate the expected time for a particular task is called:
OPR technique.
Weighted averaging.
Three-point estimating.
Duration averaging.
Expected time technique.