Question: A technique that uses optimistic, pessimistic, and realistic time to calculate the expected time for a particular task is called: critical path method. three -
A technique that uses optimistic, pessimistic, and realistic time to calculate the expected time for a particular task is called:
critical path method.
threepoint estimating.
OPR method.
weighted averaging
expected completion time analysis.