Question 23
A. a construction project is broken down into the following 8 activities:
\table[[Activity,Immediate predecessor,Time (days)],[A,-,2],[B,A,5],[C,A,4],[D,B,1],[E,C,D,6],[F,D,3],[G,F,2]]
a. What is the project completion time in days?