Question: Question 2 3 of 4 0 Your client added two new features after your team built the original backlog for its project. Since you are

Question 23 of 40
Your client added two new features after your team built the original backlog for its project. Since you are using an agile approach to the project, how should you handle this situation?
Add the features to the current iteration if the features are determined as high-priority items.
Ask your client to add the features to a future project.
Add the new features at the end of the original backlog.
Re-estimate, re-evaluate, and re-prioritize the backlog features at the beginning of the next iteration.
 Question 23 of 40 Your client added two new features after

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!