Question: Your client added two new features after your team built the original backlog for its project. Since you are using an agile approach to the

Your client added two new features after your team built the original backlog for its project. Since you are using an agile approach to the project, how should you handle this situation?

A

Re-estimate, re-evaluate, and re-prioritize the backlog features at the beginning of the next iteration.

B

Add the new features at the end of the original backlog.

C

Add the features to the current iteration if the features are determined as high-priority items.

D

Ask your client to add the features to a future project.