Question: Question 2 3 p Suppose a project's critical path consists of three activities, each with duration estimates as follows Activity Duration Estimates (days! Optimistico 7

Question 2 3 p Suppose a project's critical path
Question 2 3 p Suppose a project's critical path consists of three activities, each with duration estimates as follows Activity Duration Estimates (days! Optimistico 7 X Pessimistic to 33 Most Ukely ) 18 16 16 19 2 8 25 33 What is the standard deviation of this project's expected completion time (Round to 2 decimal places