Question: Question 2 3 pts Suppose a project's critical path consists of three activities, each with duration estimates as follows... Activity Duration Estimates (days) Optimistic (a)

Question 2 3 pts Suppose a project's critical
Question 2 3 pts Suppose a project's critical path consists of three activities, each with duration estimates as follows... Activity Duration Estimates (days) Optimistic (a) Most Likely (m) 6 17 8 19 Pessimistic (b) 32 29 Y 10 18 31 Z What is the standard deviation of this project's expected completion time? (Round to 2 decimal places)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!