Question: Question 2 3 Use the following information to develop the network diagram: Due to the issues with the supplier, Activity A 1 and A 2

Question 23
Use the following information to develop the network diagram:
Due to the issues with the supplier, Activity A1 and A2 were completed late. The actual finish is
provided in the table above. The customer still wants to finish this project in 30 days. The customer is
happy to provide more resources and budget to complete this project in 30 days.
Based on this information, which activity will you select to reduce the project duration and by how
many days to bring the project back on track?