Question: Question 2 4 ( 4 points ) A special truck that George needs on his project has been scheduled on another project. This is an

Question 24(4 points)
A special truck that George needs on his project has been scheduled on another project. This is an example of what type of resource constraint?
Working capital
People
Equipment
Information
Materials