Question: Question 2 . 4 The client of a project has requested the project team to crash 8 hours of time. The table below provides the

Question 2.4
The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing.
(a) What is the crash cost for 8 hours of time-savings?
(b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time?
\table[[Activity,\table[[Normal Duration],[(hours)]],\table[[Normal Cost],[($)]],\table[[Crash Duration],[(hours)]],\table[[Crash Cost],[(S)]],\table[[Immediate],[Predecessors]]],[A,2,10,2,0,None],[B,3,15,2,23,A],[C,5,25,4,30,B],[D,3,20,1,24,C],[E,6,30,4,45,C],[F,1,5,1,0,C, E],[G,7,35,6,50,F],[H,10,50,7,62,D, G],[Total,,$190,,,]]
 Question 2.4 The client of a project has requested the project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!