Question: Question 2.4 The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information
Question 2.4
The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing.
(a) What is the crash cost for 8 hours of time-savings?
(b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time?
| Activity | Normal Duration (hours) | Normal Cost ($) | Crash Duration (hours) | Crash Cost (S) | Immediate Predecessors |
| A | 2 | 10 | 2 | 0 | None |
| B | 3 | 15 | 2 | 23 | A |
| C | 5 | 25 | 4 | 30 | B |
| D | 3 | 20 | 1 | 24 | C |
| E | 6 | 30 | 4 | 45 | C |
| F | 1 | 5 | 1 | 0 | C,E |
| G | 7 | 35 | 6 | 50 | F |
| H | 10 | 50 | 7 | 62 | D,G |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock