Question: Question 2 ( 5 0 Points ) : Estimate the cost of constructing 3 0 columns ( 3 0 in . by 3 0 in

Question 2(50 Points):
Estimate the cost of constructing 30 columns (30 in . by 30 in . with height of 5 ft .6 in .). The
plywood and lumber for making formwork will be used two times ("2 USE"). The crew
installation hour is determined based on the fact that 4 carpenters in the crew continuously work
to make form, erect form, and remove form (carpenter labor productivity data given in Table 1).
Helpers' cost can be estimated based on labor productivity data and hourly rate as given. The
number of helpers on the project varies from time to time, dependent on carpenters' needs. Note,
45-min hour efficiency factor needs to apply to labor productivity data in Table 1 which
represents the normal circumstances at efficiency factor 1.0.
Table 1: Labor-hours required per 100 SFCA of column forms
Table 2: Hourly Rates
Based on the provided information, estimate the crew work hours on this project.
Estimate the unit cost ($ per SFCA) for crew installation (including carpenters, helpers,
and foreman).
Question 2 ( 5 0 Points ) : Estimate the cost of

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!