Question: Question 2 5 ( 1 point ) The following table shows the normal time, crash time, normal cost, and crash cost of an activity. What

Question 25(1 point)
The following table shows the normal time, crash time, normal cost, and crash cost of an activity. What is the cost of reducing the activity's duration by 5 time units
Normal time Crash time Normal cost Crash cost
2510 $190 $290
Note:
1- Do not include the dollar sign.
2- Round to 2 decimal places if your answer is not a whole number.
Your Answer: