Question: Question 2 5 3 Points Frank's Tooling operates their GTA factory one twelve - hours shift per day, seven days per week. Their design capacity

Question 25
3 Points
Frank's Tooling operates their GTA factory one twelve-hours shift per day, seven days per week. Their design capacity is 126 units per hour. Last week they produced 3980 units. What was their utilization last week?
State answer as a percent rounded to two decimal places