Question: Question 2 5 pts We have a 2 1 relay installed in substation a looking over Line A - B , as well as Line

Question 2
5 pts
We have a 21 relay installed in substation a looking over Line A-B, as well as Line B-C and Line C-D as backup protection.
Line A-B length is 44 km .
Line B-C length is 107 km .
Line C-D length is 56 km .
ZLine =0.033 per km.
In the 21 relay we need to program the impedance for the Zone 3 reach. From the given information above, calculate the primary impedance that the Zone 3 will reach to.
Hint: Primary impedance is the actual impedance of the line, so you do not have to take into account the CT and VT at this point.
Question 2 5 pts We have a 2 1 relay installed in

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Electrical Engineering Questions!