Question: Question 2 5 The correct MRP table for item E should be table [ [ Item: E , Lead Time: 1 Week ] ,

Question 25
The correct MRP table for item E should be
\table[[Item: E,Lead Time: 1 Week],[Date,1,2,3,4,5,6,7,8,9],[\table[[Gross],[Requirements]],,,,,,,2100,,],[\table[[Scheduled],[Receipts]],,,,,,,,,],[\table[[On],[Hand]],100,100,100,100,100,100,100,0,,],[\table[[Net],[Requirements]],,,,,,,2000,,],[\table[[Planned Order],[Release]],,,,,,2000,,,]]
Item: L
Lead Time: 1 Week
\table[[Date,1,2,3,4,5,6,7,8,9]]
 Question 25 The correct MRP table for item E should be