Question: The correct MRP table for item E should be o Item: E Lead Time: 1 Week Date 1 2 . 4 5 6 7 8

The correct MRP table for item E should be o Item: E Lead Time: 1 Week Date 12.4567892100 Gross Requirements Scheduled Receipts On 100 Hand Net Requirements 100100100100100100020002000 Planned Order Release O Item: E Lead Time: 1 Week Date 12.3457 CO 92100 Gross Requirements Scheduled Receipts On