Question: Question 2 6 3 pts Define what the critical path is in a project. Why are project managers trying to determine this when they are
Question
pts
Define what the critical path is in a project. Why are project managers trying to determine this when they are creating network diagrams? marks
It is the sequence of the project network activities which add up to the overall duration. This determines the time possible to complete the project. This provides the projectn