Question: Define what the critical path is in a project. Why are project managers trying to determine this when they are creating network diagrams? (4 marks)

Define what the critical path is in a project. Why are project managers trying to determine this when they are creating network diagrams? (4 marks)

It is the sequence of the( )project network activities which add up to the( )overall duration. This determines the( )time possible to complete the project. This provides the project( ).