Question: Question 2 6 ( 4 points ) One project has 4 5 activities, 1 9 of which are on the critical path. The estimated average

Question 26(4 points)
One project has 45 activities, 19 of which are on the critical path. The estimated average time for the crtical path is 120 days. The standard deviation along the critical path is 8. Please choose the correct answer by using PERT analysis. Please help the project manager to find out the proper due date so that the project eal be completed with a probability of 90%.
145.72
130.25
120
Page 260+32
138.64