Question: Question 2 6 ( 4 points ) One project has 4 5 activities, 1 9 of which are on the critical path. The estimated average
Question points
One project has activities, of which are on the critical path. The estimated average time for the crtical path is days. The standard deviation along the critical path is Please choose the correct answer by using PERT analysis. Please help the project manager to find out the proper due date so that the project eal be completed with a probability of
Page
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
