Question: Question 2 (6 points) Given the following critical path network with duration in weeks: The critical path is How long will it take to complete

Question 2 (6 points) Given the following

Question 2 (6 points) Given the following critical path network with duration in weeks: The critical path is How long will it take to complete the project? weeks What task or tasks, if any have slack? B(5) (C(6) A(7) G(3) (D(6) E(4) F(8) Blank 1: Blank 2: Blank 3