Question: Question 2 7 . 5 p t s Project managers must frequently contend with the implications of the triple constraints of cost , schedule and
Question
Project managers must frequently contend with the implications of the triple constraints of cost schedule and quality or performance Which of the following statements does NOT accurately describe a valid implication associated with this challenge?
Schedule typically functions independent of cost and technical performance.
Project managers can generally satisfy goals related to schedule and technical performance, but it may come at the expense of cost
A project may be considered successful, even if the project manager exceeds the schedule.
Project managers should consider stakeholder priorities as they address the challenge of the three constraints.