Question: Question 2 7 In project network analysis, slack refers to the difference between: observed and predicted times optimistic and pessimistic times finish and start times

Question 27
In project network analysis, "slack" refers to the difference between:
observed and predicted times
optimistic and pessimistic times
finish and start times
mean and modal times
latest and earliest times