Question: In project network analysis, slack refers to the difference between latest and earliest times. mean and modal times. observed and predicted times. finish and start
In project network analysis, "slack" refers to the difference between
latest and earliest times.
mean and modal times.
observed and predicted times.
finish and start times.
optimistic and pessimistic times.