Question: Question 2 9 The continuous footing for a building has a CLL of 7 5 0 : The specs require 5 rows of # 6

Question 29
The continuous footing for a building has a CLL of 750: The specs require 5 rows
of #6 rebar laid side by side with an 18" overlap. The rebar comes in 20' lengths.
How many 20' rebar must be ordered for this footing?
195 rebar
208 rebar
188 rebar
203 rebar