Question: Question 2 a. From the following information, please develop an activity-on-node (AON) project network. Complete the forward and backward pass: ID Description Time Predecessor None

Question 2 a. From the following information,

Question 2 a. From the following information, please develop an activity-on-node (AON) project network. Complete the forward and backward pass: ID Description Time Predecessor None A Survey site 2 B Excavate site A B 3 D Install power lines Install drainage Pour foundation B 5 E CD b. Please compute activity slack, and identify the critical path. c. How many days will the project take? (100 marks)