Question: a. From the following information, please develop an activity-on-node (AON) project network. Complete the forward and backward pass: ID Description Predecessor Time A Survey site

a. From the following information, please develop

a. From the following information, please develop an activity-on-node (AON) project network. Complete the forward and backward pass: ID Description Predecessor Time A Survey site None 2 B Excavate site A 4 Install power lines B 3 D Install drainage B 6 E Pour foundation C.D 3 b. Please compute activity slack, and identify the critical path. c. How many days will the project take? (100 marks)