Question: QUESTION 2 A ) It is required to maintain the air in a building at 2 2 C dry bulb and 5 5 % relative

QUESTION 2
A) It is required to maintain the air in a building at 22C dry bulb and 55% relative humidity when the outside conditions are 26C dry bulb and 70% relative humidity.
The total heat gains to the room (sensible plus latent) are 25 kW and the latent heat gains are 10 kW .
There is no re-circulation and the fresh air passes over a cooling coil to dehumidify it, and then a re-heater, before entering the room.
The cooling coil contact factor is 0.8, the volume flow of fresh air is 7m3s.
Calculate, using a psychometric chart where applicable:
(i) The temperature of the air leaving the cooling coil
[8 marks]
(ii) The cooling coil load
[4 marks]
(iii) The re-heater coil load
[4 marks]
Data:
cpma=1.02kJkgK
hg=2540kJkg
air=1.2kgm3
QUESTION 2 A ) It is required to maintain the air

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Mechanical Engineering Questions!