Question: Question 2 A) You are a project manager for the World Health Organization on an urgent mission to deliver medicines to villagers in an outlying

Question 2

A) You are a project manager for the World Health Organization on an urgent mission to deliver medicines to villagers in an outlying area of Somalia. There are a range of logistical issues and activities that need to be performed and you need to prepare a project plan to take into account all relevant elements of the plan and stakeholders covered in the MBA programme.

List at least 12 important activities that you need to perform in setting up the project and decide on precedence's (order of them occurring). Prepare a table indicating:

  • An estimated time for each activity
  • The precedence of each
  • A brief reason for your precedence choice.

(12 Marks)

B) You have a personality conflict between two of your team members. Describe the process by which you would resolve the issues, bearing in mind the cost, quality, and time constraints of the project.

  1. Marks)

C) Generally speaking, there is a trade-off between Time, Quality and Cost in all projects. Discuss the implications of this trade-off for the following projects:

  • A wedding
  • Building an aircraft
  • Setting an examination

(5 Marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!