Question: Question 2 Activity Optimistic time Most Likely time Pessimistic time Predecessor A 6 10 B 5 8A 6 7 9A D 20 B E 9

Question 2 Activity Optimistic time Most Likely

Question 2 Activity Optimistic time Most Likely time Pessimistic time Predecessor A 6 10 B 5 8A 6 7 9A D 20 B E 9 111c F 71 11 19 DE Tasks, precedence requirements, and time estimates for a project are shown in the table. Use the information in the table to draw the AON network for the project. Calculate ES, EF, LS, LF for the activities and slack values. What is the expected completion time of the project and the variance of the project's expected duration