Question: QUESTION 2 Assuming that you a project manager for the LOGON project which is in week 2 0 and has the following PV , AC

QUESTION 2
Assuming that you a project manager for the LOGON project which is in week 20 and has the
following PV, AC, and EV as shown in Figure 1 below.
riguie i. rivjeut status as ui ween cu.
Using the figures below:
PV=K5,120,000
AC=K5,300,000
EV=K4,290,000
Compute the following to reveal the different aspects about the status of this project:
i., Schedule variance (SV);
ii., Cost variance (CV);
iii. Schedule Performance Index (SPI); and
iv. Cost performance Index (CPI).