Question: QUESTION 2 Assuming that you a project manager for the LOGON project which is in week 2 0 and has the following PV , AC
QUESTION
Assuming that you a project manager for the LOGON project which is in week and has the
following PV AC and EV as shown in Figure below.
riguie i rivjeut status as ui ween cu
Using the figures below:
Compute the following to reveal the different aspects about the status of this project:
i Schedule variance SV;
ii Cost variance CV;
iii. Schedule Performance Index SPI; and
iv Cost performance Index CPI
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
