Question: Question 2: Below is a project WBS with cost apportioned by percent. If the total project cost is estimated to be $600,000, what are the
Question 2: Below is a project WBS with cost apportioned by percent. If the total project cost is estimated to be $600,000, what are the estimated costs for the following deliverables? Show ALL of your working to get the points on offer below! a) Design? (3 pts) b) Programming? ( 3 pts) c. In-house testing? ( 3pts) What weaknesses are inherent in this estimating approach? ( Ipt) Question 2: Below is a project WBS with cost apportioned by percent. If the total project cost is estimated to be $600,000, what are the estimated costs for the following deliverables? Show ALL of your working to get the points on offer below! a) Design? (3 pts) b) Programming? ( 3 pts) c. In-house testing? ( 3pts) What weaknesses are inherent in this estimating approach? ( Ipt)
Step by Step Solution
There are 3 Steps involved in it