Question: Question 2: Calculate the total float for each activity. 1. The following project consists of 8 activities, which have been labelled A to H Activity

Question 2: Calculate the total float for each activity.
1. The following project consists of 8 activities, which have been labelled A to H Activity Time (days) Precedence A. 3 . C. 7 A D. . . 13 F ,D G D,F 11 G,E . (a) Draw the corresponding AON network for the project (b) Calculate the total float for each activity. (c) Find all critical paths in the AON network (d) Find the minimum amount of time required to complete the project. (e) If the minimum amount of time to complete the project is 35 days, find the latest finish and times for all the activities. (f) What is the effect on minimum completion time if F is delayed by 3 days? (g) What is the effect on minimum completion time if E is delayed by 7 days