Question: Question 2 - Calculation Question A general contractor has assigned to build a new project in the UAE University. The orignal cstimate of the total
Question Calculation Question
A general contractor has assigned to build a new project in the UAE University. The orignal cstimate of the total project cost is AED. The expected propect duration is moniths and each of the activities requires approximately one month. After three and a half months: The work in activities and is completed. The work in activity is threefourths completed, and the work in activities B E and G is half completed. The incurred costs to date are AED.
What is the status of the project in terms of schedule and budget? Marks
How far along is the project? completed Marks
What is Estimate to Complete? Marks
What is expected total time to complete the project Marks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
