Question: Question 2: Cased Study Topic: Cost Management (15 Marks) You are currently running the XYZ project based on the planned schedule and cost. In the
Question 2: Cased Study Topic: Cost Management (15 Marks)
You are currently running the XYZ project based on the planned schedule and cost. In the middle of the project, the sponsors requested for a progress report and the status schedule and cost related to the project.
Given the following information for the ONE-year project, and figure out the values requested to answer the subsequent questions:
PV = RM20,500
EV = RM 33,000
AC = RM25,000
BAC = RM120,000
PLEASE SHOW THE FORMULA AND WORKING CALCULATION FOR EACH RELATED QUESTIONS.
- Calculate the cost variance and schedule variance. Interpret what each of the values means. Show the calculation
(3 marks)
- Calculate cost performance index (CPI) and schedule performance index (SPI) for the project? Show the calculation.
(4 marks)
- What is the status of schedule performance?
(2 marks)
- Explain the status of cost performance?
(2 marks)
- Calculate the estimate at completion (EAC) for this project.
(2 marks)
- Conclude the current project performance?
(2 marks)