Question: QUESTION 2 (CLO 2): Super Skid Technology Bhd has put in a bid to fabricate a new specialised injection skid for an oil rig provider.
QUESTION 2 (CLO 2):
Super Skid Technology Bhd has put in a bid to fabricate a new specialised injection skid for an oil rig provider. In the bid, a list of activities has been listed for the fabrication tasks to build the skid. These activities are shown in the table below:
| Activity | Immediate predecessors | Time/ Duration (weeks) | Direct Cost (RM) | Indirect Cost (RM |
| A | - | 15 | 2,000 | 1,500 |
| B | A | 14 | 1,800 | 1,500 |
| C | A | 14 | 1,550 | 550 |
| D | B | 18 | 4,300 | 2,000 |
| E | C, D | 17 | 3,550 | 1,500 |
| F | D, E | 16 | 3,000 | 1,550 |
| G | E | 15 | 1,400 | 1,000 |
| H | F, G | 16 | 3,200 | 1,800 |
a) Draw the network diagram (5 marks)
b) Determine the project duration (2 marks)
c) Determine the total cost of the project (2 marks)
d) Identify the critical path (1 mark).