Question: QUESTION 2 (CLO 2): Super Skid Technology Bhd has put in a bid to fabricate a new specialised injection skid for an oil rig provider.

QUESTION 2 (CLO 2):

Super Skid Technology Bhd has put in a bid to fabricate a new specialised injection skid for an oil rig provider. In the bid, a list of activities has been listed for the fabrication tasks to build the skid. These activities are shown in the table below:

Activity

Immediate predecessors

Time/ Duration (weeks)

Direct Cost (RM)

Indirect Cost (RM

A

-

15

2,000

1,500

B

A

14

1,800

1,500

C

A

14

1,550

550

D

B

18

4,300

2,000

E

C, D

17

3,550

1,500

F

D, E

16

3,000

1,550

G

E

15

1,400

1,000

H

F, G

16

3,200

1,800

a) Draw the network diagram (5 marks)

b) Determine the project duration (2 marks)

c) Determine the total cost of the project (2 marks)

d) Identify the critical path (1 mark).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!