Question: Question 2 Consider a sequential process with 3 stations. The processing time ( minutes per unit by 1 employee ) and number of employees at

Question 2
Consider a sequential process with 3 stations. The processing time (minutes per unit by 1 employee) and number of employees at each station are as follows:
Processing time
Number of Employees
6 employees
Station A: 4min? unit
Station B: 2min? unit
2 employees
Station C: 6min? unit
3 employees
What is the process capacity (for the whole process)?
20 units per hour
30 units per hour
6 units per minute
6 units per hour